August 31, 2026

Pennsylvania governor orders new rules for data centers

By:
Dallas Bond

Pennsylvania Gov. Josh Shapiro has issued an executive order setting new rules for developers seeking to build data centers in the state, with requirements focused on energy, environmental protection, transparency, workforce development, and local involvement.

The order requires data center developers to address energy, environmental, and other concerns before moving forward with new projects in Pennsylvania. It also gives municipalities a larger role in decisions about development in their communities.

Among the changes, the order removes all AI data center proposals from the Fast Track permitting process and bars the use of nondisclosure agreements for data center projects.

Developers will be required to cover the full cost of the infrastructure needed to power their projects, including new electricity generation, transmission, and distribution, without shifting those costs to Pennsylvania households and businesses.

Hiring for a mission-critical build? Get a pre-qualified shortlist.

iRecruit.co specializes in construction recruiting for data center, energy, and advanced-manufacturing projects — project managers, MEP coordinators, commissioning leads, and more. We pre-screen every candidate so only qualified professionals reach your hiring team.

Get Started

Success-based pricing · 90-day replacement credit · No upfront fee on single roles

The order also says developers must engage openly with residents and local leaders through detailed outreach plans. Those plans must include notification to impacted local governments, public meetings, and consultation early enough to allow meaningful public input on major design decisions.

In addition, developers must hire and train local workers and enter into community benefit agreements aimed at local priorities, including schools, infrastructure, and long-term economic development. They also must meet what the order describes as the highest standards for environmental protection, including strict water conservation requirements.

Data center operators will also have to submit annual information to the state’s Dept. of Environmental Protection on energy and water use. That includes total energy consumption and total natural gas consumption for the previous calendar year, the estimated average amount of energy usage per hour during the data center's peak, total water consumption for the previous calendar year along with the maximum day demand, and any measures taken to protect the environment and public from polluted water or air.

The executive order created strict requirements regarding energy affordability, community engagement, workforce and economic development, transparency, and environmental protection.

Read the source

Keywords:
Pennsylvania,data centers,executive order,energy policy,environmental protection
Free Download

Data Center Construction Labor Trends in 2026

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

More mission critical construction news

Energy Vault secures land for 125 MW Stoney Creek BESS
September 6, 2026

Energy Vault secures land for 125 MW Stoney Creek BESS

Energy Vault secures land for 125 MW / 1 GWh Stoney Creek BESS in NSW, advancing toward construction.
Sempra files permits for 27 mtpa Port Arthur LNG expansion
September 6, 2026

Sempra files permits for 27 mtpa Port Arthur LNG expansion

Sempra files permits for Port Arthur LNG North to add four trains and 27 mtpa, targeting exports by 2034.
EPMS in Data Centers: Systems, Skills & Hiring Demand
September 6, 2026

EPMS in Data Centers: Systems, Skills & Hiring Demand

EPMS links utility-to-rack power monitoring, improves commissioning and fault diagnosis, and drives hiring demand in data centers.
NETA vs NICET: Which Certification Pays More in 2026?
September 5, 2026

NETA vs NICET: Which Certification Pays More in 2026?

NETA has the higher top-end pay for high-voltage and data-center field roles; NICET offers more portable pay in fire-alarm and inspection.